CLASSIFICATION OF WORKS BY LEVEL

Classification of Construction Works by Grade under Decree 06/2021/NĐ-CP

Classification of construction works by grade is a key starting point in construction project management. It determines the level of documentation, contractor capacity, appraisal authority and acceptance procedures.

Quick overview: Construction works are divided into 5 grades: special grade, grade I, grade II, grade III and grade IV, based on height, number of storeys, floor area, structural capacity, function and overall importance.

1. Concept and importance in project management

A construction grade reflects the scale, technical complexity and significance of a work. Correctly determining the grade helps to:

  • Select appropriate contractor capacity for design, construction and supervision.
  • Identify the proper authority for appraisal and approval, as well as cost, quality and schedule management requirements.
  • Clarify the mandatory legal documents and technical standards that must be applied.
  • Avoid violations in project formulation, appraisal, approval and bidding.

In simple terms: the grade is like the “class” of a building. The more important and complex the work is, the higher its grade.

2. Legal basis

The classification of construction works by grade is based mainly on:

  • Decree 06/2021/NĐ-CP on management of construction quality, construction and maintenance of works.
  • National and sectoral technical regulations and standards applicable to each type of work.
  • Other guidelines for civil, industrial, transport, hydraulic and infrastructure works.

3. Five grades of construction works

Under current regulations, construction works are classified into five grades:

Grade Key features Management implications
Special grade Very large scale, special function, national-level impact, very high safety and technical requirements. Strict appraisal and approval procedures; contractors and experts must have exceptional capability.
Grade I Large-scale works that play an important role for a region, locality or sector. Subject to many mandatory standards; contractors must have strong experience and capacity.
Grade II Medium-scale works, common in many civil, industrial and infrastructure projects. Account for a large proportion of practical projects; clearly defined requirements but less stringent than grade I.
Grade III Smaller works, with moderate technical complexity. Suitable for small and medium-sized contractors; simpler procedures.
Grade IV Very small scale, simple structures, low risk. Streamlined procedures, shorter timelines, lower technical requirements.

4. Main criteria for determining the grade

In practice, the grade is determined using a combination of criteria. The most important include:

4.1. Height and number of storeys

  • The taller the building and the more storeys it has, the higher its grade tends to be.
  • For example, high-rise residential buildings above certain height thresholds are usually classified as grade I or even special grade, depending on detailed rules.

4.2. Floor area

  • The greater the total floor area, the higher the grade.
  • This includes usable floor area, technical areas, ancillary spaces and related infrastructure.

4.3. Structural capacity and configuration

  • Works with large loads, long spans, complicated structures or special materials are classified at higher grades.
  • Works using special structural solutions (e.g. long-span prestressed structures) often require a higher grade.

4.4. Function and overall importance

  • Works serving security, defence, critical infrastructure or central control functions are usually special grade or grade I.
  • Small detached houses for a single family are usually grade III or IV, depending on the detailed criteria.

4.5. Type of construction work

Each type of work has its own detailed criteria, for example:

  • Civil buildings: height, number of storeys, floor area, occupancy, fire safety, etc.
  • Transport works: load, traffic volume, bridge span, road length and class, etc.
  • Industrial buildings: production capacity, process characteristics, explosion/fire risk, etc.
  • Technical infrastructure: scale of power, water supply, wastewater treatment and solid waste systems.

5. Illustrative examples

Type of work Example Typical grade (for reference)
High-rise apartment building 40 storeys, about 120 m high, with 3 basement levels. Usually grade I, subject to specific criteria.
Industrial factory Steel-frame workshop, 10,000 m², large span. Often grade II.
Government office Headquarters of a provincial People’s Committee, high security requirements. Usually grade I or special grade.
Detached house Three-storey house, total floor area under 250 m². Typically grade IV or grade III (depending on criteria).
Bridge or urban flyover Urban flyover with multiple ramps and high traffic load. Often grade II or grade I.

6. Conclusion

Classification of construction works by grade is a mandatory and essential step in construction project management. Determining the correct grade at the beginning helps to:

  • Formulate, design, appraise and approve the project in compliance with regulations.
  • Select contractors with appropriate capacity and experience.
  • Reduce legal, technical and safety risks throughout the project life cycle.

*This article provides a simplified explanation for study and general project management. For actual projects, always refer directly to Decree 06/2021/NĐ-CP and current detailed guidance.*

Related Articles
Construction project management
Construction project management
Construction project management - practical knowledge information from INDUSVINA for customers, partners and professionals in Vietnam and international markets.
More Details
Latest Construction Law
Latest Construction Law
Latest Construction Law - practical knowledge information from INDUSVINA for customers, partners and professionals in Vietnam and international markets.
More Details
LESSON 3: CONSTRUCTION PROJECT OPERATING SYSTEM
LESSON 3: CONSTRUCTION PROJECT OPERATING SYSTEM
Projects do not fail because of engineering alone. They break down because operations are fragmented. Most construction projects do not collapse because the team lacks technical capability....
More Details
Article 2: THE 4 PILLARS OF PROJECT MANAGEMENT – MISS ONE PILLAR, THE SYSTEM COLLAPSES
Article 2: THE 4 PILLARS OF PROJECT MANAGEMENT – MISS ONE PILLAR, THE SYSTEM COLLAPSES
INDUSVINA Viewpoint Miss one pillar and the project doesn’t just weaken — it loses balance and collapses. Project management is building an operating system, not merely “getting tasks done....
More Details
LESSON 1: WHAT IS CONSTRUCTION PROJECT MANAGEMENT?
LESSON 1: WHAT IS CONSTRUCTION PROJECT MANAGEMENT?
In the construction industry, many people confuse: A site supervisor A construction coordinator And a true project manager. A good site supervisor can help a project progress quickly....
More Details
Lesson 2/4 – Quality
Lesson 2/4 – Quality
Quality is not just about looks, nor is it about “doing it by experience” or “finishing it and then adjusting it later”. In construction projects, QUALITY = THE DEGREE OF CONFORMITY of the...
More Details
Lesson 5/5 – Closing / Project completion according to PMI – transparent, sufficient, standard & responsible closing
Lesson 5/5 – Closing / Project completion according to PMI – transparent, sufficient, standard & responsible closing
Closing is not just “closing the file”, but the time to prove the true value of the entire project: acceptance – handover – contract closing – lessons learned – file storage, from the perspective...
More Details
LESSON 4/5: Project Monitoring & Control
LESSON 4/5: Project Monitoring & Control
If Initiating is defining the goal, Planning is drawing the map, Executing is marching, then Monitoring & Controlling is the “sword and shield” of the project manager – both attacking deviations...
More Details
Lesson 2/5 – Create a detailed, feasible, and controllable project plan
Lesson 2/5 – Create a detailed, feasible, and controllable project plan
Objectives of the Planning phase: ✔️ Define the entire scope of work ✔️ Design a clear, feasible implementation roadmap ✔️ Anticipate risks and countermeasures ✔️ Clarify quality, cost, information,...
More Details
Lesson 1/5 – Initiating – Project Initialization
Lesson 1/5 – Initiating – Project Initialization
Initiation is the “first gate” of every project: where we define what the project is, why it needs to be done, who is involved, and who is responsible. If this step is superficial, the whole...
More Details

INDUSVINA – International Standard Industrial EPC & MRO Contractor

EPC Construction – M&E Engineering – Steel Structures – Global Export Services

Trusted Partner for Industrial Plants, Manufacturing & FDI Enterprises