Inspect in the correct state.
Hand over only when safe.
A practical checklist for operations and maintenance teams: confirm access conditions, record the condition found, assign corrective work and verify readiness before returning equipment to service.
Reviewed: 18 November 2026 · Follow manufacturer instructions, site procedures and the legal requirements applicable to each asset.
Separate operating observations from maintenance intervention
While running: observe or measure only at locations designed and assessed as safe, using an approved method. Do not remove guards, touch rotating parts, adjust fasteners or insert tools into danger zones to obtain readings.
For opening equipment or entering a danger zone: follow its specific shutdown and energy-control procedure. Identify electrical, pneumatic, hydraulic, thermal, motion, suspended-load and stored-energy hazards; isolate, lock/control, release or restrain safely, then verify effectiveness before starting. [2–3]
Stop work, keep clear and notify the responsible person if there is abnormal smoke/burning odour, damaged guarding, a sudden increase in vibration, hazardous leakage or unverified isolation. Do not use a hand to locate a high-pressure fluid leak.
A short checklist by equipment state
| Group | Safe observation/measurement while operating | Checks after energy has been controlled |
|---|---|---|
| Motors, pumps, fans, gearboxes | Vibration, temperature and sound trends; load, speed and process readings. | Couplings, bearings, feet, clearances and alignment against equipment documentation. |
| Lubrication and seals | Oil level via suitable indicators, temperature and leakage signs from a safe position. | Lubricant type, seals and lubrication paths; adding grease is not a universal remedy for heat. |
| Drives and conveyors | Mistracking, slipping and impacts observed from guarded positions. | Belts, pulleys, rollers, pins and guards; no adjustment while moving. |
| Electrical and control systems | Alarms, fault history and readings at permitted interfaces/measurement points. | Connections, cables and protective devices under electrical procedures and competent personnel. |
| Piping, compressed air and hydraulics | Pressure, flow and leakage signs using safe access methods. | Valves, pipes and supports after isolation and control of retained pressure, heat and process media. |
A reference framework, not a permit or isolation procedure. Select checks by risk, equipment design and manufacturer guidance; add task-specific requirements for lifting, confined spaces, hot work and hazardous areas.
Record enough for the next person to act
Link each abnormal finding to the correct asset and location. The recipient needs to know what was checked, what could not be completed and who may authorise the next step.
| Record | Practical details |
|---|---|
| Asset and state | Asset code, location and time; running, stopped or verified isolated; relevant load/speed. |
| Finding and evidence | Leak location, abnormal sound, alarm or reading; safely obtained photographs with time and captions. |
| Initial assessment | Applicable limit or criterion, priority under the procedure, unverified matters and stop conditions. |
| Action and responsibility | Permitted immediate measures, assigned recipient, deadline, restart authoriser and verification still required. |
Where specialist measurement is needed, assign competent personnel using an approved method; retain point, units, instrument and conditions so results remain interpretable. Do not apply one vibration or temperature limit to every machine.
Assign corrective work and verify handover conditions
- Classify: normal, monitor, corrective work required or stop under approved criteria. Do not wait for a completed report when serious danger exists.
- Assign: record symptoms, evidence, scope, proposed spares, owner and deadline using the existing work-order system.
- Before testing: verify complete assembly, restored guards/protection, collected tools and people in safe positions. Lock removal, energy restoration and notification must follow the authorised procedure. [3]
- Controlled test: identify the authoriser, safe area, monitored parameters and stop criteria. If intervention must continue, shut down and re-establish energy controls first. [3]
- Handover: retain comparable before/after readings, completed work, outstanding issues and operating restrictions; operations and maintenance confirm according to assigned responsibilities.
Internal maintenance checks do not replace mandatory statutory technical safety inspections for applicable equipment. Do not release equipment for production before safety conditions are met. [1]
References and limits
- Vietnamese Law on Occupational Safety and Health — consolidated text 14/VBHN-VPQH: Article 15; clauses 2 and 5, Article 16; point a, clause 2, Article 19; Articles 30–31 on strictly regulated equipment and statutory inspections. Identify the current equipment-specific regulations, lists and procedures.
- HSE — Maintenance of work equipment: Reference guidance on safe maintenance, competence and isolation. UK guidance does not itself replace Vietnamese legal obligations.
- OSHA 29 CFR 1910.147: (d)(3)–(6): isolation, stored energy and verification; (e): restoration; (f)(1): testing and reapplication of controls. A US technical reference, not presented as a universally mandatory Vietnamese rule.
Reviewed: 18 November 2026. A framework for organising inspections, not a substitute for manufacturer documents, risk assessment or task-specific procedures. Recheck the checklist and criteria when equipment, conditions or applicable rules change. Translations are for reference; consult official Vietnamese legal texts.