Ringlock is suitable where the layout has multiple corners, elevations or intersections and work platforms need to be arranged by area. This article focuses on scaffolding for access and work at height. Where the task is to support formwork or a structure under construction, assess the shoring system against its intended function and relevant design documents.
When should you consider Ringlock?
| Situation | What to check | Documents to consult |
|---|---|---|
| Façade with multiple corners or elevations | Check available modules, platform width, access routes and actual tie locations. | Scaffold plans, elevations and layout details. |
| Repeated work by floor or section | Compare the costs of transport, erection, inspection, relocation and dismantling. | Section schedule, component list and site logistics plan. |
| Debris netting, loading bays or projecting sections | Refer these features to the designer to assess their effects on loads, ties, connections and stability. | Design documents and method statement for the actual configuration. |

Handover checklist before use
- Documentation. Confirm the approved drawings or configuration, applicable instructions, scope of use and documented load limits.
- Components and support surface. Inspect tubes, connectors, pins, bases and bearing surfaces. Confirm component compatibility against the applicable documents.
- Stability. Before releasing the scaffold for use, check bracing, ties, connections and deviations from the drawings.
- Access and edge protection. Check access routes, platforms, guardrails, toe boards and the area below against the method statement.
- Handover. A competent person inspects and records the results. Communicate which areas are released for use, the permitted loads and the status of areas being erected or dismantled.
When should work stop for reinspection?
Notify the person in charge before removing ties for façade work, adding netting or moving material staging areas. Assess the configuration, update the documents as needed and reinspect before using the affected area.
After strong winds, an impact or base settlement, or if defects are found in pins or connections, isolate the affected area and arrange reinspection by a competent person. During dismantling, follow the approved sequence and maintain stability throughout.
References
- QCVN 18:2021/BXD, Section 2.2 — Scaffolds and ladders
- HSE — Scaffolding guidance, the UK Health and Safety Executive.
- Design documents, the approved method statement and the manufacturer’s documentation for the system in use.
Explore products and exports
SCAFFOLDING · CONSTRUCTION · INSPECTION
Need to discuss a scaffold configuration?
Send the plans, elevations, work areas and support conditions so we can discuss your requirements.
SEND AN INQUIRY ↗INDUSVINA — WORK SAFELY · ACT QUICKLY · KEEP IT SIMPLE · LIVE WELL · WIN ORDERS.
ACCURATE – COMPLETE – CLEAN – UP TO DATE.