Measure the heat sources.
Choose the right solution.
Factory heat control must protect workers, suit production and have measurable acceptance criteria. Start with hot zones, heat sources and objectives, rather than the number of fans to buy.
Reviewed: 18 November 2026 · Selection and acceptance guidance; site-specific design requires a survey.
Survey four groups of data
| What to understand | What to record | Decision supported |
|---|---|---|
| People and production | Locations, shifts, workload, clothing; product temperature/humidity limits. | Protected zones and mandatory requirements. |
| Heat sources | Roof, walls, furnaces, machinery and hot pipes; schedules and operating loads. | Reduce external heat gain or control heat at source. |
| Environment and airflow | Simultaneous indoor/outdoor temperature and humidity; radiation, air speed, supply/exhaust openings and obstructions. | Ventilation, cooling and humidity-control feasibility. |
| Existing systems | Power/water, airflow and resistance, controls, hygiene, faults and installation windows. | Correct existing weaknesses or add capacity. |
Design measurements do not replace occupational-environment monitoring required by applicable regulations.

Illustration, not measured results from a specific site.
Select according to the cause
| Survey finding | Measures to consider | Conditions to check |
|---|---|---|
| Significant heat gain through roof/envelope | Suitable shading, reflection or insulation. | Roof load, structure, fire safety, condensation, leaks and maintenance. |
| Furnaces, machinery or pipes create hot spots | Shielding, source insulation, local extraction or zoning. | Exhaust contaminants and make-up air; do not transfer heat and pollution to other workers. |
| Heat accumulation or obstructed airflow | Organise supply/exhaust and adjust layout and fans. | Actual airflow against system resistance, occupied zones, dust and noise. |
| More air movement is needed | Circulation/HVLS fans where suitable. | Air movement is not the same as lower air temperature; assess actual heat-safety conditions. |
| Climate and processes tolerate added humidity | Direct evaporative cooling/Cooling Pads. | Outdoor humidity, exhaust paths, water and hygiene; performance falls in already humid air. [3] |
| Processes require controlled conditions | Air conditioning/HVAC for the necessary zones. | Cooling load, enclosure integrity, ventilation, humidity, filtration and operating cost. |
A solution often combines several measures. Eliminate options that fail safety or quality requirements before comparing prices; profit scores cannot compensate for unmet mandatory conditions.
Count all costs and challenge optimistic assumptions
- Capital: equipment, structure, power/water, installation, commissioning and production interruption.
- Operation: electricity, water, cleaning, consumables, maintenance and replacement over the same comparison period.
- Benefits: use supported data only; avoid double-counting energy savings, productivity and avoided losses.
Technical information to request before ordering equipment
Heat-load schedule and assumptions; supply/exhaust airflow; fan curves at the operating point; pressure losses; power/water, noise and maintenance requirements. Air changes per hour are only one input and do not establish satisfactory heat removal or distribution.
State electrical power in W or kW. Do not reuse formulas without units, free-air flow ratings or roof-surface temperatures as substitutes for occupied-zone temperature.
Avoid eight causes of poor results
- No baseline → record conditions by zone, shift and production load.
- Confusing circulation with ventilation → assess air movement and air exchange separately.
- Assuming the roof is the main source → measure and prioritise heat sources.
- Ignoring machine heat → treat hot spots, exhaust and safety together.
- Racks, partitions or machines obstruct airflow → review air paths without blocking escape routes.
- Evaporative cooling for humidity-sensitive products → check process limits first.
- Choosing by lowest price or catalogue capacity → compare life-cycle costs and actual operating points.
- No post-installation measurements → agree verification methods and criteria in the scope of work.
Accept against records and measurements
- Before installation: agree objectives, measurement locations/heights, times, production loads, reference weather and acceptance limits.
- During commissioning: inspect installation, safety, supply/exhaust, controls, noise, water leaks and production impacts.
- When comparing: use comparable conditions; record differences and the agreed assessment method where conditions differ.
- At handover: provide raw measurements, records, drawings, settings, operating instructions, maintenance schedules and responsible contacts.
Do not promise the same temperature reduction for every factory. Results must relate to measurement conditions, protected zones and specific criteria. Technical acceptance and microclimate compliance assessment are separate matters.
Safety is an operating condition
Combine engineering measures with suitable work practices: drinking water, cool rest areas, recovery breaks, heat acclimatisation and recognition of warning signs. Protect workers during the retrofit, rather than waiting for its completion. [2]
Sources and scope
- [1] Circular 26/2016/TT-BYT issuing QCVN 26:2016/BYT: workplace microclimate, Part II, Tables 1–2. Check the applicable persons, workload, measurements and conditions; there is no universal limit for all workstations.
- [2] NIOSH — Workplace Recommendations and Criteria for a Recommended Standard, Chapter 6: engineering and work-practice heat controls. These are technical references, not Vietnamese legislation.
- [3] U.S. DOE — Evaporative Coolers: cooling with added humidity, water management and maintenance.
Reviewed 18 November 2026. The selection table and investment sequence are INDUSVINA guidance; they do not replace site-specific design, monitoring or applicable approval records.