CONSTRUCTION TECHNOLOGY · FOUNDATION SERIES
Raft foundation construction.
Confirm inspection points before placing concrete.
A raft is a foundation slab supporting several columns or walls across an area. Inspect the founding soil and concealed layers, then confirm concrete supply, construction joints and curing before the pour.
When can the designer select a raft?
Column and wall layout
Consider a raft if separate footing bases would be close to or overlap one another, or if the design requires a common slab under multiple load points.
Bearing capacity and deformation
Check bearing capacity and total and differential settlement. If predicted settlement exceeds the criteria, assess ground improvement or compare alternative foundations.
Excavation conditions
Consider groundwater, excavation stability, impacts on adjacent structures and uplift where there is a basement.
Compare what each foundation supports. An isolated footing usually supports one column. A strip footing supports a wall or row of columns. A raft is a common slab beneath multiple load points. Selection depends on the investigation and design calculations.

Six construction control stages
| Construction stage | What to check | References and records |
|---|---|---|
| 1. Setting out and excavation | Check gridlines, levels, excavation stability and water control. Monitor impacts on neighbouring assets as required by the method statement. | Drawings, investigation report, excavation method and survey results. |
| 2. Founding soil and layers below the slab | Inspect the founding soil before blinding. Check blinding, waterproofing, protection layers or slab penetrations as detailed in the design. | Formation inspection and acceptance records for concealed layers and details. |
| 3. Reinforcement, formwork and embedded items | Check top and bottom reinforcement, supports, cover, additional reinforcement around columns, starter bars, sleeves and waterstops where applicable. | Current drawing revision, survey results and pre-pour checklist. |
| 4. Pour planning | Confirm pour sequence by zone, delivery rate, pumps and standby equipment. Identify permitted construction joint locations and how interruptions will be handled. | Pour method, delivery plan, ITP inspection points and contingency plan. |
| 5. Placement, compaction and recording | Verify delivery and concrete criteria under the project documents. Sample, place and compact under the approved method. Link delivery time, truck and samples to the pour zone. | Delivery tickets, pour log, sample IDs, test results and discrepancy records where applicable. |
| 6. Curing and release | Protect the surface, monitor curing and record temperatures when required. Verify conditions for removing protection, continuing work or applying loads. | Curing logs, temperature data where required, acceptance records and release sign-off. |
For cost estimating. Separate excavation, blinding, waterproofing where required, reinforcement, formwork and footing concrete to select the applicable norms. Use the project documents for acceptance criteria.
When concrete supply is interrupted
Worked example. During a raft pour, the next truck is late. Record the time, pour edge location, concrete condition and delivery information. Notify the responsible person so they can assess the situation against the approved method and documents.
Obtain the required sign-off and follow the approved method. Record the duration of the interruption and the affected zone.
Hold the affected work. Obtain confirmation of the location and surface preparation method, then arrange inspection before resuming the pour.
Curing and temperature control
Prepare curing materials and assign monitoring responsibilities before the pour. If the project classifies the raft as mass concrete, follow the approved thermal control plan, including sensor locations, recording intervals, limits and conditions for removing protection. Assess each raft under the applicable project documents.
- 01 Founding soil and concealed layers have been accepted.
- 02 Reinforcement, cover and embedded items have been checked.
- 03 Pour sequence, supply plan and standby equipment are ready.
- 04 The response to interruptions and construction joints has been agreed.
- 05 Staff, materials and equipment are available for curing and any required thermal monitoring.
- 06 Records link the pour zone, samples and sign-off.
References and further reading
- TCVN 9362:2026 — reference for foundation design for buildings and structures.
- TCVN 4453:1995 — construction and acceptance of cast-in-place concrete and reinforced concrete structures.
- TCVN 9341:2012 — construction and acceptance of mass concrete within the standard's scope.
- ACI · Mass concrete temperature control — further reading on how long thermal protection should be maintained. Refer to project documents for applicable conditions.
Previous article · Isolated footing construction
Related article · Strip footing construction
Foundation reading · Inspection and Test Plan (ITP)
Explore products and export offerings
FOUNDATIONS · METHOD STATEMENTS · QUALITY CONTROL
Need to discuss raft foundation works?
Share the location, support needed and available documents such as foundation drawings, geotechnical reports, concrete quantities or the pour plan.
SEND A FOUNDATION ENQUIRY ↗INDUSVINA — AN TOÀN · NHANH · GỌN · SỐNG KHỎE · TẠO ĐƠN HÀNG.
ĐÚNG – ĐỦ – SẠCH – SỐNG.